Jake has removed the substrate out of the etch chamber but after inspection of the chamber he found it was very dirty and needs to be sent for cleaning and have Teflon insulators replaced.
We will keep you updated.
Jake has removed the substrate out of the etch chamber but after inspection of the chamber he found it was very dirty and needs to be sent for cleaning and have Teflon insulators replaced.
We will keep you updated.
The replacement Pressure Controller for the STS was ordered today and expedited. I spoke with SPTS and it’s in stock in the UK and best case scenario it will be delivered this coming Tuesday.
Thanks,
INRF/BION Staff
The STS system is down due to the current ageing computer system. We are currently waiting for the new upgraded computer system to return from the UK but don’t have an ETA at this time. We will update the blog as soon as the equipment is back up. We apologize for any inconvenience.
Thanks,
INRF/BION Staff
The PlasmaTherm and MA6 are down for maintenance and should be back up Wednesday once Jake gets in. The HF room in the BION will also be closed until Wednesday.
Thanks,
INRF/BION Staff
Room 1411 will be closed today (9/25/13). We are having work done to automate the Laminar Flow Benches. The BION lab will be fully shut down this Saturday (9/28/13) to complete the rest of the facility. Sorry for any inconvenience.
Thanks,
INRF/BION Staff
MA56 Down for Maintenance. We should have it back up this coming Monday or Tuesday. The MA6 is up, sorry for the confusion.
Thanks,
INRF/BION Staff
MA56 Down for Maintenance. We should have it back up this coming Monday or Tuesday.
Thanks,
INRF/BION Staff
Lab Activity Report
August 12, 2013
To: Cleanroom Users
From: Jake Hes
The FM Plumbers are implementing a fix to the BiON humidifiers this Thursday morning 8/8/2013. In order to do so the Industrial water which currently feeds those humidifiers, and the lab hoods and general taps needs to be shutoff. The humidifiers themselves will be offline for several hours as the reroute the soft water. We anticipate it will be back online approximately 10:00am.
Thanks,
INRF/BION Staff
The upgrade for the STS is going to start on August 5th and should take approximately 2 weeks to complete.
Thanks,
INRF/BION Staff