Integrated Nanosystems Research Facility

The INRF gowning room is now back on line. You will now be able to access the cleanroom with your keycards through rm 2324 (afterhours included). All afterhours users with hard keys, please return them to Ryan asap.

INRF

  • The INRF will be closed this Saturday (08/13) in order for Facilities to perform maintenance on the compressors.
  • The DI water in the INRF is still down due to leaks within the facility. We are still working on getting these repaired.

BION

  • No after-hours use is still in effect until after the 27th (Special permission will be granted if staff is on site)
  • The exhaust issue seems to be under control but stay vigilant and pay attention to the alarms in case the issue arises again. Facilities is still investigating the cause.

 

Equipment/process training will now take place on Mondays. You will still  put in a training request through the website, then we will schedule the training for the following Monday.

During the relocation of one of the benches the contractors broke a DI water pipe. The DI water will be shut down in the INRF for a couple days until the pipe and valve can be repaired. There will be no lithography capability in the lab until that is fixed.

Be advised, Central Plant has scheduled a shutdown of the processed chilled water system this weekend. This will effect the INRF and BION cleanrooms. Most of the equipment other than lithography equipment will be down this Saturday and Sunday.

Monday is the 4h of July and a campus Holiday. There will be no office or lab staff and you will need afterhours access. Plan accordingly.

Have a great weekend!

MA6 is down

Today the contractors will continue painting the front office area so the office will be closed. There will be no front office staff on site. The INRF/BION cleanrooms will remain open and lab staff will be available at their usual times.

Tomorrow the contractors will start painting the front office area so office will be closed. There will be no front office staff on site. The INRF/BION cleanrooms will remain open and lab staff will be available at their usual times.